美国海军面临的下一个重大危机:建造和维修核潜艇似乎不可能

(May 21, 2003) -- This conceptual drawing shows the new Virginia-class attack submarine now under construction at General Dynamics Electric Boat in Groton, Conn., and Northrop Grumman Newport News Shipbuilding in Newport News, Va. The first ship of this class, USS Virginia (SSN 774) is scheduled to be delivered to the U.S. Navy in 2004. U.S. D.O.D. graphic by Ron Stern. (RELEASED)
(May 21, 2003) -- This conceptual drawing shows the new Virginia-class attack submarine now under construction at General Dynamics Electric Boat in Groton, Conn., and Northrop Grumman Newport News Shipbuilding in Newport News, Va. The first ship of this class, USS Virginia (SSN 774) is scheduled to be delivered to the U.S. Navy in 2004. U.S. D.O.D. graphic by Ron Stern. (RELEASED)
报告内容
已翻译

美国海军潜艇面临的威胁是“家中”:并非鱼雷

在大多数人看来,对美国潜艇(或更广泛的海军资产)最大的威胁可能是鱼雷攻击、近距离战斗或新型传感器,这些都使得探测潜艇变得更加容易。

哥伦比亚级战略核潜艇

哥伦比亚级战略核潜艇。图片来源:创意公用领域。

然而,现实远没有那么戏剧化:美国当前水下力量和战备的最直接制约因素,实际上是美国疲弱的工业基础。

美国攻击潜艇舰队中越来越多的潜艇因延长的维护和修理周期而被搁置,这主要是由于船厂的能力限制、劳动力约束和供应链问题。这个现实并没有争议,政府监督机构和分析人士对此的讨论也在不断增加。

从国家安全的角度来看,这里的风险非常简单:潜艇不需要被击沉就可以被使其失去作用。如果它们长时间停留在维修厂中,就无法追踪敌方潜艇或收集情报。每一艘在维修中的潜艇都是舰队中少了一艘活跃的舰艇——而且这是一个持续存在的问题。

理解当前的维护延误

海军和国会部分通过维护延误天数来跟踪潜艇的战备情况——这是一个累积指标,衡量计划的维修工作延误了多少天。

哥伦比亚级。图片来源:创意公用领域。

未来美国海军哥伦比亚级弹道导弹潜艇的艺术渲染。这12艘哥伦比亚级潜艇将替代即将达到最大延长服役寿命的俄亥俄级潜艇。计划在2021财年开始建造USS Columbia (SSBN-826),预计在2028财年交付,并在2031年开始巡逻。

国会研究服务处对潜艇战备趋势的审查总结了当时的海军少将乔纳森·拉克的评论,他表示攻击潜艇部队大约携带着

仅显示内容预览。完整文章请访问原始来源。 查看完整文章

分类信息
地区
北美
分析域
战役级
主要分类
后勤保障
SALUTE 报告
规模
N/A
活动
由于船厂能力限制、劳动力约束和供应链问题,美国海军潜艇因延长的维护和修理周期而停工。
地点
美国
单位
美国海军
时间
持续进行中
装备
哥伦比亚级战略核潜艇弗吉尼亚级攻击型核潜艇博伊西号明尼苏达号
摘要

由于公共船厂的能力限制和供应链问题,美国海军潜艇目前因延长的维护延误而停工。哥伦比亚级战略核潜艇预计将延迟12到16个月交付,影响整体海军战备。海军正在投资现代化努力,以缓解这些后勤挑战并提高潜艇维护效率。

关键事实
  • 由于工业基础问题,美国海军潜艇正经历延长的维护延误。
  • 哥伦比亚级战略核潜艇预计将延迟12到16个月交付。
  • 海军的四个公共船厂对潜艇维护至关重要,目前正面临瓶颈。
  • 维护延误导致每次潜艇平均延误225天。
  • 海军正在投资现代化努力以解决这些问题。